How does Prince2 work? A simplified example

Back to Prince2

Prince2 and modular SW in a demanding project - Case Study (Italian)

 

 

From Project's start to the end of the first operational stage

 

bulletThe management (e.g., the Programme Manager) writes the Project Mandate which usually contains an outlined Business Case 

 

 

bulletThe process Starting Up a project begins. The management chooses an Executive and, in agreement with him, the Project Manager.

The Executive and the Proj. Manager take care of organizing the rest (Organization).

The Business Case is improved, the Risk Log is created, the first Product Description (which includes all that is needed to know about the product) is written together with the customer

 

 

bulletThe Proj. Board meets, evaluates results of the Starting up a project process and authorizes the proj. start, i.e., Initiating a Project (IP) which, in Prince2, constitutes the project first stage

 

 

bulletIP expands the documentation prepared in SU and produces all that is needed for the project, in particular the PID (Proj. Initiation Document) and the Project Plan (divided into stages – at least another one in addition to IP itself)

 

 

bulletThe Project Board meets, approves the PID and baselines it (the PID becomes the “contract” between the PB and the Proj. Manager), authorizes the second stage

 

 

bulletDuring the second stage: the first time-drive report (Highlight Report) from the Project Manager to the Proj. Board had confirmed that everything was ok, but after a while an external co-operator raises an Issue – a supplier would be going to fail. The Issue becomes a Risk, the Proj. Board is informed by the Proj. Manager who suggests an alternative supplier; the Proj. Board asks the Proj. Manager for an alternative stage plan (Exception Plan) which is then approved by the Proj. Board itself. The new plan takes the place of the previous one; the entire Project Plan, the Business Case and so on are updated as foreseen by Prince2

 

 

bulletThe second stage is approaching its end: one starts planning the second stage in detail

 

 

bulletEnd of the second stage: the Proj. Board meets, checks whether the stage has produced what was foreseen and in particular whether the results are in accord with Product Descriptions, approves the next stage detailed plan and authorizes its start

Cyclic phase with an Exception Plan

 

bulletThe project is now in a cyclic phase

 

 

bulletDuring the fourth stage, thanks to a dedicated process (MP), the Proj. Manager discovers that the quality of the products which should be delivered by an external team does not meet Product Descriptions; those products are not accepted, but the necessary corrective action implies that time tolerances will be excelled.

The PB is informed and receives the recommendation either to reduce the Scope (i.e., to accept products with reduced functionalities) or increase the budget. The PB approves the second solution, a new Stage Plan (Exception Plan) is prepared to take the new situation into account, and the project goes on

 

 
bullet Project closure: it is approved by the Proj. Board. Moreover, the Project Board approves a series of documents such as the Lessons Learned Report, the Follow-on Action Recommendations, customer support recommendations and so on. The Organization is disbanded

 

 

bulletAfter the Prince2 project – in this case one year,  the Executive takes part in a meeting (planned during the project) during which the project final benefits are evaluated.

 

 

 

 

 

Visit our free Newsletter "Misfits of project management"

 

 

 

 

 

 

Operations

Operations in Ticino, Switzerland, Italy, Europe. In particolar, we bring Project Management, Prince2 and the other solutions to: Lugano, Zurich, Milan, Rome, London and the UK, France.

 

 

 

 

 

 

 

 

 
bullet

Back to Prince2

 
bullet

Prince2 and modular SW in a demanding proj. - Case Study (Italian)

 

 

Contacts

 

central(at)righetconsult.com

 

Lugano - Paradiso, Ticino, Switzerland

Home | Up | Solutions and results | How we work | Project Management | Case studies | Documents | Newsletter | About | Links | Contacts | Sitemap

All the information/materials on this site are provided on an "as is" basis, and they are not intended in any way to be comprehensive. Whoever uses this site does so at his/her own risk and is advised to take independent professional advice before acting on any information/materials found here. No responsibility is accepted and no representations or warranties, express or implied, that any of the information and materials on this site are complete, accurate or error/omission-free, are given.
Unless specifically stated, the contents of this site may not be reproduced, distributed or published in any way without prior consent.

This site makes use of  Google Analytics, a web analysis service by Google, Inc. ("Google"); relevant conditions apply.
Last updated: 08/01/14.